16 September 2014 - Day one, site set out, excavation underway
22 September 2014 - Drainage installed, piles poured.
18 October 2014 -Frames & Trusses under way.
31 October 2014 – Trusses completed.
8 November 2014 – Roofing and Brickwork taking shape.
14 December 2014 – Roof completed, render underway.
8 January 2015 – Eve linings underway.
21 September 2015 – The Finished product.